Penn State Health Milton S. Hershey Medical Center Case Study

Penn State Health Milton S. Hershey Medical Center Case Study

May 22, 2017
|
0 Comments
|

OptimumLOOP™ delivers operational efficiencies and beats expected cost savings.

IntroductionHershey CS Details

Since 2009, the Penn State Health Milton S. Hershey Medical Center has been implementing a multiphase energy efficiency program. Six years into the program, Kevin Kanoff, the center’s campus energy engineer, knew the chiller plants were efficient—but he believed they could be improved. Johnson Controls, the center’s lead vendor, brought in Optimum Energy to perform an engineering site assessment (ESA), which proved him correct: optimizing the chiller plants across the campus would deliver significant energy savings.

After Optimum Energy completed the installation of its OptiCx™ platform and OptimumLOOP in June 2016, the center’s 12 chillers were running at peak efficiency, saving electricity costs, using less water, and reducing carbon emissions. In fact, annual energy savings were found to be almost 4.2 GWh/year, roughly 1 GWh more than expected, and campus energy intensity dropped 4 percent.

Challenge: Optimizing a Large, Efficient Plant

The plant optimization project was not a small task. The Milton S. Hershey Medical Center serves more than 1.2 million patients and employs 10,000 people. The campus—which includes two hospitals, five institutes, and Penn State College of Medicine—has 2.6 million square feet of air-conditioned building space served by three chiller plants: a central plant of eight chillers and two

Solution: A Holistic System with Real-Time Analytics and Relational Control

Optimum Energy’s OptimumLOOP relational control provided a solution that optimizes the plant holistically—it automatically stages all the chillers and the chilled-water storage tank as an integrated whole, choosing the best option based on equipment efficiency and demand for cooling. The software continuously collects data about plant operations, outside conditions, and hundreds of other parameters, and calculates how to operate for peak efficiency and operational stability. It then adjusts the set points of pumps, fans, and other components in real time. The result of combining this system with the data analytics of the OptiCx platform is what Optimum Energy calls True Optimization®

The implementation at all three plants went smoothly, says Kanoff. “From a building environment perspective, the system went through start-up seamlessly. Critical patient areas were not compromised.”

Optimization also streamlined chiller operations that staff had performed manually without a complete picture of the system.

Result: Energy and Cost Savings Beyond Expectations

The payoff goes well beyond ease of operation. OptimumLOOP reduced the center’s energy intensity by 4 percent, bringing the campuswide reduction to 24 percent over 2009 levels.

“We initially projected an energy savings of 3.4 GWh annually, but the electric utility’s evaluator found that savings are actually 4.16 GWh annually,” says Kanoff. That translates into electricity costs savings of about $300,000 a year; he originally projected that the system would save $261,000 a year. As a bonus, the medical center earned a onetime $416,000 incentive from the utility.

Download the full case study here.

Share on FacebookTweet about this on TwitterShare on LinkedInShare on Google+Email this to someone